Judging from Commissioner McKeel’s reaction the East County courthouse construction could start in December 2010
|
Source: The Gresham Outlook (Apr 20, 2010)
Judging from Commissioner Diane McKeel’s smile following Tuesday’s briefing on the East County courthouse project, the embattled building is likely to become a reality.
The five-member board of commissioners will decide on Thursday, April 22, whether to build the structure, more than 25 years in the works.
During its Tuesday meeting, county commissioners considered both two-courtroom and three-courtroom configurations for the building, which is proposed for county-owned land on SE 185th Ave and Stark St in Rockwood. Get Map!
Depending on the number of courtrooms, the project could cost between $17.4 million and $20.7 million. A few million dollars from selling surplus county land south of Edgefield in Troutdale is earmarked for the courthouse. The rest of the money most likely will be financed through bonds.
County commissioners seemed to like the idea of moving ahead with the project now to take advantage of the weak construction market and low interest rates.
If approved, construction could start in December, with the building finished in early 2012.